The main objective of this project is to install a solid waste treatment plant based on TERI's Enhanced Acidification and Methanation (TEAM) technology at PTS township, NTPC Farakka. This plant would treat 100 kg of organic waste generated from the kitchen. TERI will supply the TEAM equipment, erect, and commission the plant. The biogas produced from the plant will be used for partial replacement of LPG in the kitchen; and the manure will be used for horticulture purposes.